Hyderabad Regional Ring Road (RRR) Status 2026: North, South, Cost, Villages and Land Compensation
The Regional Ring Road is built in two parts. The north (Sangareddy to Choutuppal, about 161.5 km) has nearly all land acquired and awaits Union Cabinet approval; the south (about 201 km) has a Cabinet-approved alignment and a DPR with the Centre. Costs, mandals, villages and compensation as reported.
Quick answer: Hyderabad's Regional Ring Road (RRR) is about 340 km in total (newspapers give figures between 334 and 363 km) and is built in two parts. The north part (Sangareddy to Choutuppal, about 161.5 km) has almost all its land acquired and has been out to tender, but Union Cabinet approval is still reported as pending. The south part (Choutuppal to Sangareddy, about 201 km) has an alignment approved by the Telangana Cabinet and a detailed project report (DPR) sent to the Centre, but the Union Ministry of Road Transport and Highways (MoRTH) has not yet decided on it. All figures below are as reported in the news and may change.
Last updated: 23 November 2026. Compiled from news reports and government statements; every number is attributed to its source. Where reports disagree, both figures are shown.
RRR status at a glance
| North part | South part | |
|---|---|---|
| Route | Sangareddy, Narsapur, Toopran, Gajwel, Jagdevpur, Bhongir, Choutuppal | Choutuppal, Amangal, Chevella, Vikarabad, Sangareddy (greenfield) |
| Length | About 161.5 km (reports say 158 to 161.5 km) | About 201 km (earlier 182 to 189 km options) |
| Lanes | Six lanes (earlier tender notice said four) | Six lanes |
| Estimated cost | ₹23,935.6 crore per Union Minister Nitin Gadkari's reply (reported 6 Aug 2026) | About ₹16,000 crore: about ₹6,500 crore land compensation and about ₹9,500 crore construction (Deccan Chronicle, March 2026) |
| Land | Section 3D notified for 99.06% and compensation awards declared for 87.19% (Gadkari's reply); Chief Minister said 95% acquired (14 July 2026) | About 2,010 hectares; 4,962 acres across 90 villages in six districts to be acquired (Chief Secretary review, 19 Nov 2026) |
| Where it stands | Tender deadline extended repeatedly; only Union Cabinet (CCEA) approval reported pending | State Cabinet approved the alignment on 23 June 2025; MoRTH has not decided (Telangana Tribune, 19 Oct 2026) |
North part: Sangareddy to Choutuppal
The northern stretch was declared National Highway 161AA in 2017 and is under Bharatmala Pariyojana Phase-I. In-principle approval for the northern part came in February 2021 (Telangana Today, 6 August 2026). The State agreed to bear 50 percent of the land acquisition cost.
Construction tender
NHAI's tender notice split the 161.5 km into five packages:
- Package 1: Girmapur (Sangareddy) to Reddipalle, 34.5 km
- Package 2: Reddipalle to Islampur, 26 km
- Package 3: Islampur to Pragnapur, 23 km
- Package 4: Pragnapur to Rayagiri, 43 km
- Package 5: Rayagiri to Tangadpalle, 35 km
The first tender notice (December 2024) described a four-lane road and gave a cost of over ₹7,104 crore (Hyderabad Mail). Later reports describe a six-lane road to be built under the Hybrid Annuity Model at ₹23,935.6 crore. The sixth extension of the bid deadline, to 20 August, was reported on 6 August 2026, and a further extension to 23 September 2026 was reported on 25 August 2026 (Telangana Today). Bidders have not been named in the reports we reviewed.
What is still pending
"Except for approval from the Cabinet Committee on Economic Affairs, all other clearances for the northern part have reportedly been secured" (Telangana Today, 25 August 2026). On 14 July 2026 the Chief Minister asked Union Minister Nitin Gadkari to secure the Union Cabinet's approval and said 95 percent of the northern land acquisition was complete. In a reply dated 29 July, Mr Gadkari said the DPR was appraised and the timeline would be finalised after feasibility study and competent-authority approval. On 9 October the State's Roads and Buildings Minister announced that land acquisition for the northern section was complete (Telangana Tribune, 19 October 2026).
Note: R&B officials were quoted in August as saying about 60 percent of acquisition was complete. These figures measure different things (notifications, awards, possession), so they are not directly comparable.
South part: Choutuppal to Sangareddy
The Telangana Cabinet approved a new 201 km six-lane alignment on 23 June 2025. Three options were considered: 189.5 km (about 96 percent agricultural land, with some forest), 201 km (about 99 percent agricultural land, no forest) and 218 km (needing forest clearance). The 201 km option was chosen to avoid lengthy forest clearances (Deccan Chronicle, 27 June 2025; Telangana Tribune, 24 September 2025).
- Land: about 2,010 hectares, affecting 55 habitations or structures (Deccan Chronicle). On 19 November 2026, officials told the Chief Secretary that 4,962 acres across 90 villages in six districts must be acquired (Telangana Today).
- Districts: reports name Yadadri Bhuvanagiri, Nalgonda, Rangareddy, Mahbubnagar, Nagarkurnool, Vikarabad and Sangareddy (seven); the Chief Secretary review mentions six, so the exact district count differs by report.
- Highways crossed: NH-65, NH-44, NH-163, NH-19 and NH-76.
- Cost sharing: the Centre is expected to bear construction cost, and Telangana to bear 50 percent of land compensation.
- Centre's status: the DPR was sent to MoRTH in March 2026. As of 19 October 2026, MoRTH had "not yet decided" on the alignment because the stretch is not covered by any central scheme, and Telangana has asked for it to be included.
Which villages and mandals are covered?
2025 HMDA notification: districts and mandals
On 31 August 2025, HMDA issued a primary notification for a 100-metre-wide RRR alignment inside the Hyderabad Metropolitan Region. Siasat reported that it covers 8 districts, 33 mandals and 163 revenue village panchayats, with the road roughly 30 to 50 km beyond the ORR. The mandals it listed:
- Ranga Reddy: Amangal, Farukh Nagar, Keshampet, Kondurg, Madgul, Talakondapalle
- Vikarabad: Mominpet, Nawabpet, Pudur, Vikarabad
- Nalgonda: Chandur, Chintapally, Marriguda, Munugodu
- Sangareddy: Hatnura, Kondapur, Sadashivpet, Sangareddy
- Siddipet: Gajwel, Jagdevpur, Markook, Rayapol, Vargal
- Medak: Narsapur, Shivampet, Toopran
- Yadadri Bhuvanagiri: Choutuppal, Narayanapur, Bhuvanagiri, Turkpally, Valigonda, Yadagirigutta
- Mahabubnagar: Balanagar
One other outlet (Newsmeter) described the same eight districts, 33 mandals and 163 villages as not affected, which contradicts Siasat and its own route list. We follow Siasat; check the notification itself. The figure of "1,355 villages and 104 mandals" refers to the whole HMDA jurisdiction, not the RRR.
2022 gazette: villages named for the northern part
In April 2022 the Centre issued gazette notifications for two units (Hans India, 23 April 2022):
- Yadadri-Bhongir unit (about 208.6 hectares): Gandhamalla, Virareddypalle, Konapur, Ibrahimpur, Dattayapalle, Velupupalle, Mallapur and Dattarpalle.
- Andole-Jogipet unit (about 108.9 hectares): Shivampeta, Vendikol, Venkatakishtapur (Angadi), Lingampally and Korpol.
In August 2022 notifications for four more units covered about 698 hectares in Sangareddy, Bhongir, Gajwel and Narsapur (Telangana Today, 26 August 2022).
The complete village-by-village list with survey numbers is in HMDA's official order on the RRR, which we could not reproduce here. Open the official document (PDF, large file of about 57 MB, scanned pages): HMDA order G.O.Ms. No. 19 on the Regional Ring Road (PDF), and check your own survey number there. Other orders are on the HMDA website (GOs and Acts). The objection deadline for the 2025 HMDA notification was 15 September 2025.
Land compensation and market prices
- In October 2024 the State revised compensation, "doubled or even tripled" in several areas, according to the Deccan Chronicle. Examples per acre: Turkapally mandal, from ₹3.37 to 6.75 lakh to ₹6.85 to 11.47 lakh; Sangareddy and Sadasivapet, from ₹4.5 lakh to ₹15 lakh.
- Telangana Tribune (19 October 2026) reported compensation ranging from about ₹16 lakh per acre in remote areas to over ₹1.27 crore per acre in high-value pockets.
- Telangana Today (January 2025) put market values at ₹50 lakh to ₹5 crore per acre depending on distance from the city, and reported farmers' demand for at least 75 percent of market value.
These figures measure different things (registration value, compensation, market value) and should not be compared directly. Aptlok has not verified any price rise on land near the RRR; claims of specific per-acre prices from videos or listings are unverified.
Timeline of key events
- February 2021: in-principle approval for the northern part.
- April and August 2022: gazette notifications for northern land units.
- October 2024: State revises compensation rates.
- December 2024: NHAI tender notice for the northern part.
- 23 June 2025: Telangana Cabinet approves the 201 km southern alignment.
- 31 August 2025: HMDA primary notification for the 100 m alignment.
- March 2026: southern DPR sent to the Centre.
- 14 and 29 July 2026: Chief Minister's request to Mr Gadkari; Mr Gadkari's reply.
- August to September 2026: northern bid deadline extended repeatedly.
- 9 and 19 October 2026: northern land acquisition declared complete; southern alignment awaits MoRTH.
- 19 November 2026: Chief Secretary reviews southern land acquisition (4,962 acres, 90 villages).
Where reports disagree
- Total length: 334 to 363 km (about 340 km most often).
- Northern cost: ₹5,554 crore, ₹7,104 crore and ₹23,935.6 crore across different reports and years.
- Northern land acquired: 60, 95 and 99.06 percent, depending on who is speaking and what is measured.
- Southern districts: six or seven; southern cost earlier reported at ₹6,480 crore before the alignment was revised.
What this means if you own or plan to buy land near the RRR
Check the official notifications for your survey number, confirm with the Sub-Registrar and the Telangana Dharani portal, and do not rely on a seller's claim about the road. Land inside an alignment can be acquired, and dates depend on approvals that are still pending.
Sources and disclaimer
Compiled from news reports in Telangana Today, Deccan Chronicle, Telangana Tribune, The South First, Siasat, Hyderabad Mail, The Hans India, The Daily Pioneer and Newsmeter, and from HMDA's website. Costs, lengths and dates are as reported and may change. Aptlok is not affiliated with HMDA, NHAI or any government agency. This article is for information only; verify with official sources before making any decision.
Frequently Asked Questions
What is the current status of the Hyderabad Regional Ring Road?
How long is the Regional Ring Road?
How much will the RRR north part cost?
How much will the RRR south part cost?
Which districts and mandals does the RRR pass through?
Where can I find the full list of RRR villages?
What compensation are RRR land owners getting?
When will the Regional Ring Road be completed?
Sources