Upcoming Flyovers in Hyderabad 2027: 5 Projects, Cost, Length and Dates
Five flyover and elevated-corridor projects in Hyderabad: IIIT Junction, Khajaguda, KBR Park, Uppal–Narapally and Miyapur–Allwyn. Length, cost and target dates as reported in the news.
AptLok Team
November 23, 2026
Quick answer: Five major flyover and elevated-corridor projects are in progress or planned in Hyderabad: IIIT Junction (Gachibowli), Khajaguda Junction, KBR Park (Jubilee Hills to Punjagutta), Uppal–Narapally on NH 163, and Miyapur–Allwyn X Road. News reports give target dates between April and June 2027 for three of them, and no fixed dates yet for the other two. All dates and costs below are as reported in the news and may change.
Last updated: 22 November 2026. Figures are taken from news reports and GHMC statements and are targets or estimates, not guarantees.
Watch the full map-based walkthrough (in Telugu, with English and Hindi subtitles): Upcoming flyovers in Hyderabad, start to end on the map.
Hyderabad flyover projects at a glance
| Project | What is being built | Length | Cost (as reported) | Target (as reported) |
|---|---|---|---|---|
| IIIT Junction, Gachibowli | 3 steel flyovers + 1 underpass | 3.39 km | Not clearly reported | May 2027 |
| Khajaguda Junction | 1 flyover + 1 underpass | 1.625 km | Not clearly reported | April or May 2027 (reports differ) |
| KBR Park, Jubilee Hills to Punjagutta | One 6-lane steel flyover | 4.3 km | ₹1,090 crore | About two years after approvals |
| Uppal–Narapally, NH 163 | Elevated corridor | About 6.2 km | ₹425 crore estimate in 2018; since revised upwards | June 2027 |
| Miyapur–Allwyn X Road | 6-lane flyover + 2 underpasses | About 1.8 km | ₹530 crore estimate | Two years from the contract |
1. IIIT Junction, Gachibowli
Traffic from Gachibowli, Lingampally, Wipro Junction and the Kondapur road meets at IIIT Junction, one of the busiest junctions in Hyderabad's IT corridor. The plan is a signal-free network of three steel flyovers and one underpass, 3.39 km in total.
- Flyover 1: ISB Road to DLF Road, four lanes in both directions, 720 m.
- Flyover 2: DLF Road to Lingampally, three lanes in one direction, 948 m.
- Flyover 3: ISB Road to Gachibowli, three lanes, 1.2 km, the longest of the three.
- Underpass: Gachibowli to Lingampally, six lanes, 520 m.
Progress: According to news reports on 18 November, 43 of the 54 pillars to be built are complete, about 80 percent. The target is May 2027. News reports in July also mentioned delays on this project, so treat the date as a target.
2. Khajaguda Junction
Right next to IIIT Junction, Khajaguda gets a flyover from the Nanakramguda side towards Shaikpet and an underpass from Shaikpet towards Gachibowli. The total length is 1.625 km, with three lanes each, one direction each.
Dates: An 18 July report says Khajaguda should finish by April 2027, while a 21 July report gives May 2027 for both junctions together. No news report gives a clear cost, so none is stated here.
3. KBR Park, Jubilee Hills to Punjagutta
The original plan was seven steel flyovers and seven underpasses around KBR Park, 14 works in total. It was sanctioned in October 2024 at ₹826 crore, and news reports say the cost later rose to ₹1,090 crore for only 2.6 km. That plan was set aside in favour of one large steel flyover.
- Route: from near the Jubilee Hills Check Post to NFCL Junction, Punjagutta.
- Size: 4.3 km, six lanes, both directions.
- Cost: ₹1,090 crore in two packages: Package 1, Jubilee Hills Check Post to Mugdha Junction, ₹580 crore; Package 2, Mugdha Junction to Muffakham Jah College, ₹510 crore, with a ramp to Banjara Hills Road No. 1.
- Approvals: the GHMC Standing Committee approved it on 3 October, but officials were asked to prepare new designs and cost estimates. According to some reports, state government and General Body approvals are still needed.
- Savings claim: GHMC says the new plan saves about ₹1,200 crore (₹800 crore on land, ₹400 crore on construction). The Daily Pioneer reports this saving is disputed, and a Deccan Chronicle report called it nominal.
- Trees: there is an eco-sensitive zone around KBR Park. GHMC says the new plan has zero footprint in that zone. No news report gives a count of trees affected.
4. Uppal–Narapally elevated corridor
This elevated corridor on National Highway 163 links Hyderabad with Warangal, Bhongir, Bibinagar (AIIMS) and Jangaon. News reports put the length at about 6.2 km, and the project has central government funds. The estimate was ₹425 crore when it began in 2018 and has risen since. The original target of Dasara 2026 has passed, and officials now aim for June 2027.
5. Miyapur–Allwyn X Road
Traffic from Hafeezpet, Bachupally and Nizampet merges on this stretch. GHMC is building a six-lane flyover of about 1.8 km over Anjaiah Nagar, with two three-lane, one-way underpasses: Hafeezpet to Miyapur, and Bachupally to Allwyn X Roads. The estimate is ₹530 crore (₹330 crore construction, ₹200 crore land). The contract went to Shivasatya Engineering, the lowest bidder, and the work must be completed in two years.
What does signal-free mean?
At a normal junction, vehicles from four sides stop in turn. A flyover lets one direction pass over the junction and an underpass lets another pass beneath it, so those flows no longer wait at the signal.
Frequently asked questions
Which flyovers are being built in Hyderabad in 2027?
The five projects covered here are IIIT Junction (Gachibowli), Khajaguda Junction, KBR Park (Jubilee Hills to Punjagutta), Uppal–Narapally on NH 163, and Miyapur–Allwyn X Road, as reported in the news.
When will the IIIT Junction flyover be ready?
News reports give a target of May 2027. According to an 18 November report, 43 of 54 pillars are complete. Earlier reports mentioned delays, so the date is a target, not a guarantee.
How much will the KBR Park steel flyover cost?
News reports put the cost at ₹1,090 crore: ₹580 crore for Package 1 and ₹510 crore for Package 2. Final approvals are reported to be pending.
How long is the KBR Park flyover?
The new corridor is 4.3 km, with six lanes in both directions, from near the Jubilee Hills Check Post to NFCL Junction in Punjagutta.
When will the Uppal–Narapally elevated corridor open?
The current target reported is June 2027. The earlier target of Dasara 2026 has passed.
What is the Miyapur–Allwyn flyover project?
A six-lane flyover of about 1.8 km over Anjaiah Nagar with two underpasses, at an estimated ₹530 crore, to be completed within two years of the contract.
Why do the Khajaguda dates differ between reports?
A July 18 report says April 2027 for Khajaguda, while a July 21 report says May 2027 for both Khajaguda and IIIT Junction together. We say early 2027 until an official date is announced.
Sources and disclaimer
Information is compiled from news reports (including The Daily Pioneer, Deccan Chronicle, Siasat, OneIndia and Hyderabad Mail) and GHMC statements. Costs and dates are estimates and targets and may change. Check official GHMC announcements before making any decision. Aptlok is not affiliated with GHMC or any government agency. This article is for information only.
Planning to buy or rent near these corridors? Browse verified listings and locality guides on Aptlok.
Read Also